Heathhall Dumfries

Below you will find details on the development size & location as well as site plans, house styles, photographs, internal walk through videos, drone footage and a 360° walkthrough where available.

We purchased the site on 31 March 2021 from Springfield properties to deliver 64 new houses and flats for rent.

Springfield will be the main contractor appointed by the Association and work started on site in May 2021.

With a 98 week contract period, the anticipated completion date for the project will be around October 2022.

DEVELOPMENT

Heathhall

Completion Date

October 2022

AREA

Dumfries & Galloway

HEATHHALL FLYOVER
A brief drone flyover of the site before works started.